Why are software development task estimations regularly off by a factor of 2-3? 
Added 8 days ago by Chad Mazzola
Show info
Why are software development task estimations regularly off by a factor of 2-3? 
Info
Michael Wolfe's answer: Let's take a hike on the coast from San Francisco to Los Angeles to visit our friends in Newport Beach. I'll whip out my map and draw our route down the coast: The line is about 400 miles long; we can walk 4 miles per hour for 10 hours per day, so we'll be there in 10 da...